KING'S LEIGH
DAHUA DACLAND
COMMUNITY UPDATE
OCTOBER 2017
VIEW PROJECT UPDATE ONLINE
King's Leigh has recently reached many exciting milestones, and overall there has been steady progress made to all stages under construction.

Stage 8 has achieved practical completion and the King's Leigh sales office has been removed to make way for stage 9b site establishment.

Another major milestone which is nearing is the intersection opening of Tindale Boulevard; this will signify the permanent closure of Maygrand Avenue and we will share further details and dates as they come available.

Stage 5
Site establishment and initial road drainage to stage 5 have been finalised, with road excavation and drainage pit construction presently underway and due for completion over the coming weeks.
 
Stage 7
Stage 7 is progressing very well, with concrete works, electrical and nbn completed and road pavement layer works in progress. Final works such as topsoil application and line marking are being finalised in readiness to achieve council practical completion. 
 
Stage 8
All final works have been completed and we are pleased to announce that stage 8 has reached practical completion. Stage 8 is now going through the auditing process by the relevant authorities, after which council will issue the Statement of Compliance. We will be in contact over the coming fortnight with further instructions for valuers to attend site.
 
Stages 9b & 10
Site establishment continues at stages 9b & 10 with bulk earthworks to be carried out over the coming weeks, after which sewer works will commence.
 
STAGE STATUS EXPECTED TITLE DATE
3 Titles Issued Titles Issued
4 Titles Issued Titles Issued
5 Road Excavation, Subsurface Improvements and Drainage Q1 2018
6 Titles Issued Titles Issued
7 Final works Q4 2017
8 Authority Approvals Underway October 2017
9b Site Establishment Q1 2018
10 Site Establishment Q1 2018
11 Construction Approval Q2 2018
 
 
 
 
   
 
 
CONSTRUCTION VIDEO
We also have a video to help you better understand the construction process and what we do behind the scenes. To learn more about what to expect while waiting for your land.
CLICK TO WATCH OUR VIDEO
 
 
LIVING TODAY
Living Today is a quarterly publication featuring a snapshot of what is going on in and around Dacland's communities.
FIND OUT MORE
 
 
customercare@dacland.com.au
facebook   instagram
DAHUA DACLAND UDIA
All possible efforts have been made to ensure the accuracy and reliability of information and representations contained within this communication. King's Leigh its consultants, agents and related entities accept no responsibility and disclaim all liability in respect to any errors or inaccuracies it may contain. Prospective purchasers should make their own enquiries to verify the information contained herein.

Sent by Dacland Pty Ltd. ABN 65 087 025 269
Level 1, 20 Wilson Street
South Yarra, Victoria Australia 3141

Unsubscribe | Privacy policy